Uniformat G3030
Storm manhole
Also called storm maintenance hole
Service life
Years in service. One stated life so far; the band will widen as sources are added.
Basis
- 50 years · Kenora: AF-6-1 Tangible Capital Asset Policy (By-law 34-2026), p16 · “Storm Sewers - Manholes” (accounting life)Capital asset policy (amortization period). Approved on text check: the label and value were found on the cited page.
- 50 years · Severn: By-law 2019-04, Corporate Policy Manual: Tangible Capital Asset Policy, Useful Life Guide, p403 · “Infrastructure - Water & Sewer - Storm Manhole” (accounting life)Capital asset policy (amortization period). Approved on text check: the label and value were found on the cited page.
How sources are chosen and recorded: sourcing policy.
Municipal lives for storm sewer (G3030)
26 municipalities in Ontario state a life for storm sewer as a whole, in 26 distinct tables: 20–150 years, median 50. 57 rows come from capital asset policies (accounting lives, used for amortization) and 43 from asset management plans (planning lives, used to forecast replacement). They describe the system rather than this component, and none is a measured life.
Years. Each dot is one stated life and each bar a stated range; equal values stack. Hollow marks are planning lives from asset management plans; filled marks are accounting lives from policies. The dashed line is the median. Policies that copy the same table count once.
All 99 stated lives
| Municipality | As written | Years | Kind | Source |
|---|---|---|---|---|
| Kenora | Storm Sewers - Culvert - STL | 20 | accounting | p16 · 2026 |
| Severn | Infrastructure - Roads - Ditches | 20 | accounting | p402 · 2019 |
| Barrie | Low Impact Development | 25 | planning | p127 · 2025 |
| Greater Sudbury | Ponds | 25 | planning | p30 · 2023 |
| Kapuskasing | Culverts - Steel | 25 | accounting | p15 · 2009 |
| Kenora | Storm Sewers - Pipe - STL | 25 | accounting | p16 · 2026 |
| London | SWM Green Infrastructure | 25 | planning | p127 · 2023 |
| Meaford | Linear - Road Surface - Asphalt - Ditch | 25 | accounting | p20 · 2020 |
| Severn | Infrastructure - Roads - Major Culverts | 25 | accounting | p402 · 2019 |
| The Blue Mountains | Linear - Road Top - Asphalt - Ditch | 25 | accounting | p12 · 2019 |
| Meaford | Linear - Culverts - Corrugated Steel | 25–40 | accounting | p19 · 2020 |
| Greater Sudbury | CSP Storm Sewer | 30 | planning | p30 · 2023 |
| Grey Highlands | Culverts | 30–40 | accounting | p10 · 2026 |
| York | Corrugated steel pipe culverts: Replacement | 35 | planning | p53 · 2024 |
| York | Storm pipe replacement | 35–75 | planning | p53 · 2024 |
| York | Outfall replacement | 35–75 | planning | p53 · 2024 |
| York | Culverts under three metres: Replacement or relining | 35–75 | planning | p53 · 2024 |
| Halton | Stormwater Pumping Stations | 39 | planning | p110 · 2025 |
| Brockton | Storm Drains - Metal - Corrugated | 40 | accounting | p3 · 2009 |
| Chapple | Culverts - steel | 40 | accounting | p1 |
| Essex | Stormwater Mains | 40 | planning | p74 · 2025 |
| Kirkland Lake | Culverts | 40 | accounting | p10 · 2020 |
| Meaford | Linear - Stormwater Facility | 40 | accounting | p19 · 2020 |
| Rainy River | Drainage | 40 | accounting | p11 · 2010 |
| Severn | Buildings/Structures - Water & Sewer - Intake Outfall Line | 40 | accounting | p400 · 2019 |
| The Blue Mountains | Linear - Culverts - Corrugated Steel | 40 | accounting | p12 · 2019 |
| The Blue Mountains | Linear - Stormwater Facility | 40 | accounting | p12 · 2019 |
| The Blue Mountains | Linear - Road Base - Asphalt - Ditch | 40 | accounting | p12 · 2019 |
| Trent Lakes | Culverts | 40 | accounting | p10 · 2009 |
| Amherstburg | Infrastructure - Storm Water - Stormwater System | 50 | accounting | p7 · 2026 |
| Barrie | Storm Sewers (Steel) | 50 | planning | p127 · 2025 |
| Barrie | Culverts (Remaining Assets) | 50 | planning | p127 · 2025 |
| Barrie | Filtration Devices | 50 | planning | p127 · 2025 |
| Barrie | Sediment Removal Devices | 50 | planning | p127 · 2025 |
| Greater Madawaska, Quinte West · same table | Culverts | 50 | accounting | p17, p37 · 2025 |
| Greater Sudbury | Oil and Grit Separators | 50 | planning | p30 · 2023 |
| Grey Highlands | Catch Basins | 50 | accounting | p10 · 2026 |
| Kapuskasing | Storm Sewer System - PVC / CI | 50 | accounting | p15 · 2009 |
| Kapuskasing | Storm Sewer System - Concrete | 50 | accounting | p15 · 2009 |
| Kenora | Storm Sewers - Pipe - Conc/PE/PVC | 50 | accounting | p16 · 2026 |
| Kenora | Storm Sewers - Culvert - PE/PVC | 50 | accounting | p16 · 2026 |
| Kenora | Storm Sewers - Manholes | 50 | accounting | p16 · 2026 |
| Kenora | Storm Sewers - Catch Basins | 50 | accounting | p16 · 2026 |
| Kingston | Roads and Related - Storm sewer | 50 | accounting | p15 · 2016 |
| Kirkland Lake | Storm Sewer System - PVC / CI, Concrete | 50 | accounting | p10 · 2020 |
| London | Minor Culverts (between 1.8m to 3m span) | 50 | planning | p158 · 2023 |
| London | Major Culverts (greater than and equal to 3m span) | 50 | planning | p158 · 2023 |
| Meaford | Linear - Road Base - Asphalt - Ditch | 50 | accounting | p19 · 2020 |
| Prince Edward | Storm - Storm Mains (Pooled) | 50 | accounting | p34 · 2022 |
| Prince Edward | Storm - Catch basins | 50 | accounting | p34 · 2022 |
| Prince Edward | Storm - Outlets | 50 | accounting | p34 · 2022 |
| Sarnia | Catch Basins | 50 | accounting | p2 |
| Severn | Infrastructure - Water & Sewer - Catch Basins | 50 | accounting | p402 · 2019 |
| Severn | Infrastructure - Water & Sewer - Double Catch Basins | 50 | accounting | p402 · 2019 |
| Severn | Infrastructure - Water & Sewer - Catch Basin Manhole | 50 | accounting | p403 · 2019 |
| Severn | Infrastructure - Water & Sewer - Double Catch Basin Manhole | 50 | accounting | p403 · 2019 |
| Severn | Infrastructure - Water & Sewer - Storm Manhole | 50 | accounting | p403 · 2019 |
| Severn | Infrastructure - Water & Sewer - Storm Sewers | 50 | accounting | p403 · 2019 |
| Simcoe | Stormwater Outlets | 50 | planning | p92 · 2025 |
| Simcoe | Stormwater Sewers | 50 | planning | p92 · 2025 |
| Simcoe | Stormwater Ponds | 50 | planning | p92 · 2025 |
| Simcoe | Storm Ponds | 50 | accounting | p21 · 2025 |
| Simcoe | Storm Sewers | 50 | accounting | p21 · 2025 |
| Simcoe | Structural Culverts | 50 | accounting | p21 · 2025 |
| York | Oil grit separator replacement | 50 | planning | p53 · 2024 |
| Meaford | Linear - Culverts - HDPE / PVC | 50–80 | accounting | p19 · 2020 |
| Toronto | Conveyance - Linear Infrastructure (Local & Trunk Sewers) | 50–150 | planning | p379 · 2025 |
| Greater Sudbury | AC Sewer | 55 | planning | p30 · 2023 |
| Essex | Culverts | 60 | planning | p60 · 2025 |
| London | Minor Culverts (Up to 1.8m in diameter) | 60 | planning | p127 · 2023 |
| Quinte West | Storm Water Ponds | 60 | accounting | p38 · 2024 |
| Rainy River | Sewer/Storm Sewer | 60 | accounting | p11 · 2010 |
| Sarnia | Storm Sewers | 60 | accounting | p2 |
| York | Maintenance hole replacement | 60 | planning | p53 · 2024 |
| York | Catch basin and ditch inlet replacement | 60 | planning | p53 · 2024 |
| Greater Sudbury | Catch Basin | 70 | planning | p30 · 2023 |
| Greater Sudbury | Maintenance Hole | 70 | planning | p30 · 2023 |
| Kapuskasing | Culverts - Concrete | 70 | accounting | p15 · 2009 |
| Barrie | Storm Sewers (Remaining Assets) | 75 | planning | p127 · 2025 |
| Barrie | Culverts (Concrete) | 75 | planning | p127 · 2025 |
| Brockton | Storm Drains - Plastic | 75 | accounting | p3 · 2009 |
| Brockton | Storm Drains - Concrete | 75 | accounting | p3 · 2009 |
| Grey Highlands | Storm Sewers Pipe | 75 | accounting | p10 · 2026 |
| Kingston | Land Improvements - Storm water ponds | 75 | accounting | p14 · 2016 |
| Meaford | Linear - Culverts - Concrete | 75 | accounting | p19 · 2020 |
| Simcoe | Culverts - Concrete | 75 | planning | p68 · 2025 |
| Simcoe | Culverts - Corrugated Steel | 75 | planning | p68 · 2025 |
| The Blue Mountains | Linear - Culverts - Concrete | 75 | accounting | p12 · 2019 |
| York | Concrete culverts: Replacement | 75 | planning | p53 · 2024 |
| Greater Sudbury | HDPE Storm Sewer | 80 | planning | p30 · 2023 |
| London | Minor Treatment | 80 | planning | p127 · 2023 |
| Welland | Sanitary & Storm Sewers (by component) - Catchbasins & Leads | 80 | accounting | p9 · 2021 |
| Greater Sudbury | Concrete Sewer | 90 | planning | p30 · 2023 |
| Barrie | Storm Sewers (Asbestos Cement, Vitrified Clay) | 100 | planning | p127 · 2025 |
| London | Storm sewers <450mm diameter | 100 | planning | p127 · 2023 |
| London | Storm sewers 450mm>= to <1,500mm diameter | 100 | planning | p127 · 2023 |
| London | Storm sewers >=1,500 mm diameter | 100 | planning | p127 · 2023 |
| London | Open Conveyance | 100 | planning | p127 · 2023 |
| London | Storm Water Management Facilities | 100 | planning | p127 · 2023 |
Each row was matched to its page automatically: the label and the number appear in the text of the cited page. An editor has not yet compared every row with the table, so follow the page link before relying on one. About the policies · All approved rows as JSON
Preventive maintenance
3 tasks in 1 work order.
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12Annual
Months from the schedule start. Download the tasks as CSV for a CMMS, or ask the MCP tool get_pm_schedule for dated visits.
Annual · 3 tasks
Source: TSPWG Manual 3-260-03.04-6 Inspection of Pavement Drainage Systems, Table 2-1 Inspection Schedule for Catch Basins, Manholes, Handholes, and Drop Inlets
Frequencies are ISO 8601 durations in the data (P3M = every 3 months).
Open questions
- These are Ontario accounting lives from municipal capital asset policies, not planning or observed replacement data.
Know the answer? Send it with a source to [email protected].
Cite this
Citation
unfinished.one (2026). Storm manhole, v0.2.0. https://unfinished.one/c/storm-manhole/v/0.2.0BibTeX
@misc{unfinished_storm_manhole_0_2_0,
title = {Storm manhole},
author = {{unfinished.one}},
year = {2026},
version = {0.2.0},
url = {https://unfinished.one/c/storm-manhole/v/0.2.0},
note = {CC BY 4.0}
}Licence CC BY 4.0 · How to cite · JSON · Versions: 0.2.0, 0.1.0