unfinished.one

Uniformat D1010

Wheelchair platform lift

1 preventive maintenance tasks for wheelchair platform lift, from published sources. No source that meets our sourcing policy states a service life yet.

Also listed as Vertical platform lift, VPL, wheelchair lift, accessibility lift

  • Maintenance only
  • Version 0.3.0 (permanent link)
  • Reviewed 2026-10-22

Service life

No service life yet. No published source that meets our sourcing policy states a life for this component, so we give none rather than guess. The maintenance tasks below are sourced. Know a public-domain or openly licensed source? Send it to [email protected].

Municipal lives for conveying (D10)

9 municipalities in Ontario and British Columbia state a life for conveying as a whole, in 9 distinct tables: 20–35 years, median 20. These come from capital asset policies: accounting lives, used for amortization. They describe the system rather than this component, and none is a measured life.

Median 20 yearsGrey Highlands: Elevator, hydraulic; Elevator, traction, 20 yearsKenora: Elevator, hydraulic; Elevator, traction, 20 yearsPrince Edward: Elevator, hydraulic; Elevator, traction, 20 yearsSarnia: Elevator, hydraulic; Elevator, traction, 20 yearsSevern: Elevator, hydraulic; Elevator, traction, 20 yearsWelland: Elevator, hydraulic; Elevator, traction, 20 yearsParksville: Elevator, hydraulic; Elevator, traction, 25 yearsBrockton: Elevator, hydraulic; Elevator, traction, 35 yearsGreater Madawaska: Conveying, 25–30 years010203040

Years. Each dot is one stated life and each bar a stated range; equal values stack. The dashed line is the median. Policies that copy the same table count once.

All 9 stated lives
MunicipalityCoversYearsKindSource
Grey HighlandsElevator, hydraulic; Elevator, traction20accountingp11 · 2026
KenoraElevator, hydraulic; Elevator, traction20accountingp15 · 2026
Prince EdwardElevator, hydraulic; Elevator, traction20accountingp34 · 2022
SarniaElevator, hydraulic; Elevator, traction20accountingp1
SevernElevator, hydraulic; Elevator, traction20accountingp400 · 2019
WellandElevator, hydraulic; Elevator, traction20accountingp8 · 2021
ParksvilleElevator, hydraulic; Elevator, traction25accountingp9 · 2023
Greater MadawaskaConveying25–30accountingp17 · 2025
BrocktonElevator, hydraulic; Elevator, traction35accountingp2 · 2009

Every row was matched to its page automatically (the label and number appear in the page text). Follow the page link before relying on an automatically matched row. About the policies · All approved rows as JSON

Preventive maintenance

1 tasks in 1 work order.

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6Semi
  7. 7
  8. 8
  9. 9
  10. 10
  11. 11
  12. 12Semi

Months from the schedule start. Download the tasks as CSV for a CMMS, or ask the MCP tool get_pm_schedule for dated visits.

Semi-annual · 1 task

Source: NAVFAC MO-118 Inspection of Vertical Transportation Equipment, 6.5 Handicapped Lifts

TaskPage
Inspect wheelchair and stair liftsp165

Frequencies are ISO 8601 durations in the data (P3M = every 3 months).

Open questions

  • No service life yet: no published source that meets the sourcing policy states one. The maintenance tasks are sourced.
  • Elevator tasks come from NAVFAC MO-118 (1988), which restates the elevator code tests of its time; check them against the current ASME A17.1 and local requirements.

Know the answer? Send it with a source to [email protected].

Cite this

Citation

unfinished.one (2026). Vertical platform lift, v0.3.0. https://unfinished.one/c/platform-lift/v/0.3.0

BibTeX

@misc{unfinished_platform_lift_0_3_0,
  title = {Vertical platform lift},
  author = {{unfinished.one}},
  year = {2026},
  version = {0.3.0},
  url = {https://unfinished.one/c/platform-lift/v/0.3.0},
  note = {CC BY 4.0}
}

Licence CC BY 4.0 · How to cite · JSON · Versions: 0.3.0, 0.2.0, 0.1.0