Uniformat G3030
Stormwater management pond
Also called SWM pond, stormwater facility, detention pond
Service life
Years in service. The band runs from the shortest to the longest life the sources state, so it shows how much they disagree, not how long 80% of units last. The line is the median of the stated lives.
Basis
- 50 years · CNA e-Tool Estimated Useful Life Table, p1 · HUD CNA 3.2.2.5 “Stormwater mgmt ponds” — U.S. Department of Housing and Urban Development (planning life)Same life for family and elderly properties. US multifamily housing. HUD's row is for site work at US multifamily properties, not municipal networks.
- 25 years · Greater Sudbury: Enterprise Asset Management Plan (2023), p30 · “Ponds” (planning life)Asset management plan (planning life). Approved on text check: the label and value were found on the cited page.
- 25 years · Halton: Halton Region 2025 Asset Management Plan, p110 · “Storm Water Ponds” (planning life)Asset management plan (planning life). Compared with an image of the cited page.
- 75 years · Kingston: Tangible Capital Assets Policy, p14 · “Land Improvements - Storm water ponds” (accounting life)Capital asset policy (amortization period). Approved on text check: the label and value were found on the cited page.
- 40 years · Meaford: By-law 2020-83, Tangible Capital Asset Policy, Appendix A Estimated Useful Lives, p19 · “Linear - Stormwater Facility” (accounting life)Capital asset policy (amortization period). Approved on text check: the label and value were found on the cited page.
- 60 years · Quinte West: A09-POLICY-0034 Tangible Capital Asset Policy, p38 · “Storm Water Ponds” (accounting life)Capital asset policy (amortization period). Approved on text check: the label and value were found on the cited page.
- 50 years · Simcoe: County of Simcoe 2025 Asset Management Plan, p92 · “Stormwater Ponds” (planning life)Asset management plan (planning life). Approved on text check: the label and value were found on the cited page.
- 50 years · Simcoe: POL-FIN-004 Tangible Capital Assets Policy (Schedule 3 to AUC 2026-046), p21 · “Storm Ponds” (accounting life)Capital asset policy (amortization period). Approved on text check: the label and value were found on the cited page.
- 40 years · The Blue Mountains: POL.COR.19.04 Tangible Capital Assets Policy, p12 · “Linear - Stormwater Facility” (accounting life)Capital asset policy (amortization period). Approved on text check: the label and value were found on the cited page.
How sources are chosen and recorded: sourcing policy.
Municipal lives for storm sewer (G3030)
27 municipalities in Ontario state a life for storm sewer as a whole, in 27 distinct tables: 20–150 years, median 50. 60 rows come from capital asset policies (accounting lives, used for amortization) and 50 from asset management plans (planning lives, used to forecast replacement). They describe the system rather than this component, and none is a measured life.
Years. Each dot is one stated life and each bar a stated range; equal values stack. Hollow marks are planning lives from asset management plans; filled marks are accounting lives from policies. The dashed line is the median. Policies that copy the same table count once.
All 109 stated lives
| Municipality | As written | Years | Kind | Source |
|---|---|---|---|---|
| Kenora | Storm Sewers - Culvert - STL | 20 | accounting | p16 · 2026 |
| Severn | Infrastructure - Roads - Ditches | 20 | accounting | p402 · 2019 |
| Barrie | Low Impact Development | 25 | planning | p127 · 2025 |
| Greater Sudbury | Ponds | 25 | planning | p30 · 2023 |
| Halton | Storm Water Ponds | 25 | planning | p110 · 2025 |
| Kapuskasing | Culverts - Steel | 25 | accounting | p15 · 2009 |
| Kenora | Storm Sewers - Pipe - STL | 25 | accounting | p16 · 2026 |
| London | SWM Green Infrastructure | 25 | planning | p127 · 2023 |
| Meaford | Linear - Road Surface - Asphalt - Ditch | 25 | accounting | p20 · 2020 |
| Severn | Infrastructure - Roads - Major Culverts | 25 | accounting | p402 · 2019 |
| The Blue Mountains | Linear - Road Top - Asphalt - Ditch | 25 | accounting | p12 · 2019 |
| Meaford | Linear - Culverts - Corrugated Steel | 25–40 | accounting | p19 · 2020 |
| Greater Sudbury | CSP Storm Sewer | 30 | planning | p30 · 2023 |
| Grey Highlands | Culverts | 30–40 | accounting | p10 · 2026 |
| York | Corrugated steel pipe culverts: Replacement | 35 | planning | p53 · 2024 |
| York | Storm pipe replacement | 35–75 | planning | p53 · 2024 |
| York | Outfall replacement | 35–75 | planning | p53 · 2024 |
| York | Culverts under three metres: Replacement or relining | 35–75 | planning | p53 · 2024 |
| Halton | Stormwater Pumping Stations | 39 | planning | p110 · 2025 |
| Brockton | Storm Drains - Metal - Corrugated | 40 | accounting | p3 · 2009 |
| Chapple | Culverts - steel | 40 | accounting | p1 |
| Essex | Stormwater Mains | 40 | planning | p74 · 2025 |
| Kirkland Lake | Culverts | 40 | accounting | p10 · 2020 |
| Meaford | Linear - Stormwater Facility | 40 | accounting | p19 · 2020 |
| Rainy River | Drainage | 40 | accounting | p11 · 2010 |
| Severn | Buildings/Structures - Water & Sewer - Intake Outfall Line | 40 | accounting | p400 · 2019 |
| The Blue Mountains | Linear - Culverts - Corrugated Steel | 40 | accounting | p12 · 2019 |
| The Blue Mountains | Linear - Stormwater Facility | 40 | accounting | p12 · 2019 |
| The Blue Mountains | Linear - Road Base - Asphalt - Ditch | 40 | accounting | p12 · 2019 |
| Trent Lakes | Culverts | 40 | accounting | p10 · 2009 |
| Amherstburg | Infrastructure - Storm Water - Stormwater System | 50 | accounting | p7 · 2026 |
| Barrie | Storm Sewers (Steel) | 50 | planning | p127 · 2025 |
| Barrie | Culverts (Remaining Assets) | 50 | planning | p127 · 2025 |
| Barrie | Filtration Devices | 50 | planning | p127 · 2025 |
| Barrie | Sediment Removal Devices | 50 | planning | p127 · 2025 |
| Greater Madawaska, Quinte West · same table | Culverts | 50 | accounting | p17, p37 · 2025 |
| Greater Napanee | Storm Sewer System: Manholes | 50 | accounting | p17 · 2012 |
| Greater Sudbury | Oil and Grit Separators | 50 | planning | p30 · 2023 |
| Grey Highlands | Catch Basins | 50 | accounting | p10 · 2026 |
| Halton | Culvert =>3m | 50 | planning | p107 · 2025 |
| Halton | Culvert <3m | 50 | planning | p107 · 2025 |
| Halton | Storm Mains | 50 | planning | p110 · 2025 |
| Halton | Oil Grit Seperator (OGS) | 50 | planning | p110 · 2025 |
| Halton | Minor Culverts (Storm) | 50 | planning | p110 · 2025 |
| Kapuskasing | Storm Sewer System - PVC / CI | 50 | accounting | p15 · 2009 |
| Kapuskasing | Storm Sewer System - Concrete | 50 | accounting | p15 · 2009 |
| Kenora | Storm Sewers - Pipe - Conc/PE/PVC | 50 | accounting | p16 · 2026 |
| Kenora | Storm Sewers - Culvert - PE/PVC | 50 | accounting | p16 · 2026 |
| Kenora | Storm Sewers - Manholes | 50 | accounting | p16 · 2026 |
| Kenora | Storm Sewers - Catch Basins | 50 | accounting | p16 · 2026 |
| Kingston | Roads and Related - Storm sewer | 50 | accounting | p15 · 2016 |
| Kirkland Lake | Storm Sewer System - PVC / CI, Concrete | 50 | accounting | p10 · 2020 |
| London | Minor Culverts (between 1.8m to 3m span) | 50 | planning | p158 · 2023 |
| London | Major Culverts (greater than and equal to 3m span) | 50 | planning | p158 · 2023 |
| Meaford | Linear - Road Base - Asphalt - Ditch | 50 | accounting | p19 · 2020 |
| Prince Edward | Storm - Storm Mains (Pooled) | 50 | accounting | p34 · 2022 |
| Prince Edward | Storm - Catch basins | 50 | accounting | p34 · 2022 |
| Prince Edward | Storm - Outlets | 50 | accounting | p34 · 2022 |
| Sarnia | Catch Basins | 50 | accounting | p2 |
| Severn | Infrastructure - Water & Sewer - Catch Basins | 50 | accounting | p402 · 2019 |
| Severn | Infrastructure - Water & Sewer - Double Catch Basins | 50 | accounting | p402 · 2019 |
| Severn | Infrastructure - Water & Sewer - Catch Basin Manhole | 50 | accounting | p403 · 2019 |
| Severn | Infrastructure - Water & Sewer - Double Catch Basin Manhole | 50 | accounting | p403 · 2019 |
| Severn | Infrastructure - Water & Sewer - Storm Manhole | 50 | accounting | p403 · 2019 |
| Severn | Infrastructure - Water & Sewer - Storm Sewers | 50 | accounting | p403 · 2019 |
| Simcoe | Stormwater Outlets | 50 | planning | p92 · 2025 |
| Simcoe | Stormwater Sewers | 50 | planning | p92 · 2025 |
| Simcoe | Stormwater Ponds | 50 | planning | p92 · 2025 |
| Simcoe | Storm Ponds | 50 | accounting | p21 · 2025 |
| Simcoe | Storm Sewers | 50 | accounting | p21 · 2025 |
| Simcoe | Structural Culverts | 50 | accounting | p21 · 2025 |
| York | Oil grit separator replacement | 50 | planning | p53 · 2024 |
| Meaford | Linear - Culverts - HDPE / PVC | 50–80 | accounting | p19 · 2020 |
| Toronto | Conveyance - Linear Infrastructure (Local & Trunk Sewers) | 50–150 | planning | p379 · 2025 |
| Greater Sudbury | AC Sewer | 55 | planning | p30 · 2023 |
| Essex | Culverts | 60 | planning | p60 · 2025 |
| London | Minor Culverts (Up to 1.8m in diameter) | 60 | planning | p127 · 2023 |
| Quinte West | Storm Water Ponds | 60 | accounting | p38 · 2024 |
| Rainy River | Sewer/Storm Sewer | 60 | accounting | p11 · 2010 |
| Sarnia | Storm Sewers | 60 | accounting | p2 |
| York | Maintenance hole replacement | 60 | planning | p53 · 2024 |
| York | Catch basin and ditch inlet replacement | 60 | planning | p53 · 2024 |
| Greater Sudbury | Catch Basin | 70 | planning | p30 · 2023 |
| Greater Sudbury | Maintenance Hole | 70 | planning | p30 · 2023 |
| Kapuskasing | Culverts - Concrete | 70 | accounting | p15 · 2009 |
| Barrie | Storm Sewers (Remaining Assets) | 75 | planning | p127 · 2025 |
| Barrie | Culverts (Concrete) | 75 | planning | p127 · 2025 |
| Brockton | Storm Drains - Plastic | 75 | accounting | p3 · 2009 |
| Brockton | Storm Drains - Concrete | 75 | accounting | p3 · 2009 |
| Greater Napanee | Storm Sewer System: Catch Basins | 75 | accounting | p17 · 2012 |
| Grey Highlands | Storm Sewers Pipe | 75 | accounting | p10 · 2026 |
| Halton | Retention Structure | 75 | planning | p110 · 2025 |
| Kingston | Land Improvements - Storm water ponds | 75 | accounting | p14 · 2016 |
| Meaford | Linear - Culverts - Concrete | 75 | accounting | p19 · 2020 |
| Simcoe | Culverts - Concrete | 75 | planning | p68 · 2025 |
| Simcoe | Culverts - Corrugated Steel | 75 | planning | p68 · 2025 |
| The Blue Mountains | Linear - Culverts - Concrete | 75 | accounting | p12 · 2019 |
| York | Concrete culverts: Replacement | 75 | planning | p53 · 2024 |
| Greater Sudbury | HDPE Storm Sewer | 80 | planning | p30 · 2023 |
| London | Minor Treatment | 80 | planning | p127 · 2023 |
| Welland | Sanitary & Storm Sewers (by component) - Catchbasins & Leads | 80 | accounting | p9 · 2021 |
| Greater Napanee | Storm Sewer System: Drains | 90 | accounting | p17 · 2012 |
| Greater Sudbury | Concrete Sewer | 90 | planning | p30 · 2023 |
| Barrie | Storm Sewers (Asbestos Cement, Vitrified Clay) | 100 | planning | p127 · 2025 |
| London | Storm sewers <450mm diameter | 100 | planning | p127 · 2023 |
| London | Storm sewers 450mm>= to <1,500mm diameter | 100 | planning | p127 · 2023 |
| London | Storm sewers >=1,500 mm diameter | 100 | planning | p127 · 2023 |
| London | Open Conveyance | 100 | planning | p127 · 2023 |
| London | Storm Water Management Facilities | 100 | planning | p127 · 2023 |
Of 110 rows, 10 were compared with an image of their page; 100 were matched to their page automatically (the label and number appear in the page text). Follow the page link before relying on an automatically matched row. About the policies · All approved rows as JSON
Preventive maintenance
12 tasks in 6 work orders. Intervals that fall due together are one visit: the every 20 years visit also covers the monthly, quarterly, semi-annual, annual and every 5 years tasks.
- 1Monthly
- 2Monthly
- 3Qtr
- 4Monthly
- 5Monthly
- 6Semi
- 7Monthly
- 8Monthly
- 9Qtr
- 10Monthly
- 11Monthly
- 12Annual
Months from the schedule start. Download the tasks as CSV for a CMMS, or ask the MCP tool get_pm_schedule for dated visits.
Monthly · 1 task
Source: Stormwater Wet Pond and Wetland Management Guidebook (EPA 833-B-09-001), Section 2 Inspection Frequency
| Task | Page |
|---|---|
| Inspect pond for minor items (debris, clogging, erosion) | p24 |
Quarterly · 2 tasks
Source: Public Buildings Service Preventive Maintenance Guide (Public Buildings Maintenance Standards), ARCS-SWM-09-03M Stormwater Management - Ponds, Wet Ponds, Spillway and Erosion
Semi-annual · 1 task
Source: Public Buildings Service Preventive Maintenance Guide (Public Buildings Maintenance Standards), ARCS-SWM-09-06M Stormwater Management - Ponds, Wet Ponds, Mow Buffer
| Task | Page |
|---|---|
| Mow the buffer and pond embankment where turf | p86 |
Annual · 6 tasks
| Task | Source |
|---|---|
| Inspect structural components (major inspection items) | Stormwater Wet Pond and Wetland Management Guidebook (EPA 833-B-09-001), p24 |
| Exercise and lubricate valves | Stormwater Wet Pond and Wetland Management Guidebook (EPA 833-B-09-001), p51 |
| Inspect mechanical components (valves, aerators, fountains, control panels) | Stormwater Wet Pond and Wetland Management Guidebook (EPA 833-B-09-001), p20 |
| Clean up shoreline: remove trash, debris and floatables | Public Buildings Service Preventive Maintenance Guide (Public Buildings Maintenance Standards), p84 |
| Full maintenance inspection of pond | Public Buildings Service Preventive Maintenance Guide (Public Buildings Maintenance Standards), p84 |
| Open the riser and test the valves | Public Buildings Service Preventive Maintenance Guide (Public Buildings Maintenance Standards), p84 |
Every 5 years · 1 task
Source: Stormwater Wet Pond and Wetland Management Guidebook (EPA 833-B-09-001), Table 2.3 Maintenance Activities and Schedules (Ponds)
| Task | Page |
|---|---|
| Remove sediment from forebays (when 60% of volume is lost) | p27 |
Every 20 years · 1 task
Source: Stormwater Wet Pond and Wetland Management Guidebook (EPA 833-B-09-001), Table 2.3 Maintenance Activities and Schedules (Ponds)
| Task | Page |
|---|---|
| Remove sediment from main pond cells (when 50% of volume is lost) | p27 |
Frequencies are ISO 8601 durations in the data (P3M = every 3 months).
Open questions
- HUD gives planning lives for US multifamily housing; the municipal rows are Ontario accounting lives. Neither is observed replacement data.
- The guidebook says its maintenance suggestions are guidance, not federal requirements.
- Written for GSA contracted O&M in US federal buildings; job plans are generic and defer to manufacturer instructions, and the fire extinguisher plans only point to NFPA 10.
Know the answer? Send it with a source to [email protected].
Cite this
Citation
unfinished.one (2026). Stormwater management pond, v0.5.0. https://unfinished.one/c/stormwater-pond/v/0.5.0BibTeX
@misc{unfinished_stormwater_pond_0_5_0,
title = {Stormwater management pond},
author = {{unfinished.one}},
year = {2026},
version = {0.5.0},
url = {https://unfinished.one/c/stormwater-pond/v/0.5.0},
note = {CC BY 4.0}
}Licence CC BY 4.0 · How to cite · JSON · Versions: 0.5.0, 0.4.0, 0.3.0, 0.2.0, 0.1.0