Uniformat D5010
Transformer, dry-type
Also called dry type transformer, XFMR, transformer
Service life
Years in service. One stated life so far; the band will widen as sources are added.
One source. This value rests on a single document (Energy Conservation Program: Energy Conservation Standards for Distribution Transformers (final rule), 89 FR 29834, April 22, 2024, p113). Treat it as that source's figure, not a settled life, until others confirm it.
Basis
- 32 years · Energy Conservation Program: Energy Conservation Standards for Distribution Transformers (final rule), 89 FR 29834, April 22, 2024, p113 · IV.F.8 “Transformer Service Lifetime: "a distribution of lifetimes, with an estimated average of 32 years and a maximum of 60 years"” — U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy (planning life)Printed page 29946. Covers all distribution transformers, including low-voltage dry-type (building dry-type) and medium-voltage liquid-immersed (pad-mounted). Mean of a distribution; the maximum is 60 years. Same value also stated on p.5 (printed 29838) and in Table IV summary on p.101 (printed 29934).
How sources are chosen and recorded: sourcing policy.
Municipal lives for electrical (D50)
39 municipalities in Ontario, British Columbia and Alberta state a life for electrical as a whole, in 30 distinct tables: 10–50 years, median 20. 47 rows come from capital asset policies (accounting lives, used for amortization) and 7 from asset management plans (planning lives, used to forecast replacement). They describe the system rather than this component, and none is a measured life.
Years. Each dot is one stated life and each bar a stated range; equal values stack. Hollow marks are planning lives from asset management plans; filled marks are accounting lives from policies. The dashed line is the median. Policies that copy the same table count once.
All 45 stated lives
| Municipality | As written | Years | Kind | Source |
|---|---|---|---|---|
| Kingston | Electrical Equipment | 10 | accounting | p15 · 2016 |
| Grey Highlands | Exterior Lighting | 15 | accounting | p11 · 2026 |
| Meaford | Electrical - Exterior Lighting | 15 | accounting | p17 · 2020 |
| The Blue Mountains | Exterior Lighting | 15 | accounting | p11 · 2019 |
| Fort St. James, Revelstoke, Rossland, Sicamous, Tumbler Ridge · same table | Electrical/Plumbing/Fire | 15–20 | accounting | p5, p9, p7, p9, p5 · 2010 |
| Okanagan-Similkameen | Electrical/Plumbing/Fire | 15–20 | accounting | p11 · 2023 |
| Salmo | Electrical/Plumbing/Fire | 15–20 | accounting | p6 · 2016 |
| Lloydminster | Permanent Structures - Electrical | 20 | accounting | p11 · 2023 |
| Lloydminster | Portable Structures - Electrical | 20 | accounting | p11 · 2023 |
| Comox Valley | HVAC systems, mechanical, plumbing, wiring, etc. | 20 | accounting | p6 · 2010 |
| Cranbrook | HVAC, plumbing, lighting, etc | 20 | accounting | p9 · 2010 |
| Parksville | Electrical Infrastructure | 20 | accounting | p9 · 2023 |
| Telkwa | Electrical/Plumbing/Fire | 20 | accounting | p8 |
| Amherstburg | Mechanical/Electrical - HVA, Lighting, Security systems, Electrical Panel | 20 | accounting | p8 · 2026 |
| Grey Highlands | Interior Lighting | 20 | accounting | p11 · 2026 |
| Grey Highlands | Ice Surface Lighting | 20 | accounting | p11 · 2026 |
| Huron | Patrol Yards - Building Electrical | 20 | planning | p42 · 2025 |
| Huron | Property Services - Building Electrical | 20 | planning | p57 · 2025 |
| Huron | Housing - Building Electrical | 20 | planning | p68 · 2025 |
| Huron | Homes for the Aged - Electrical | 20 | planning | p77 · 2025 |
| Kenora | Buildings - Electrical System | 20 | accounting | p15 · 2026 |
| London | Building Components - Services (HVAC, lighting, communication, plumbing etc.) | 20 | accounting | p2 · 2023 |
| Meaford | Electrical - Interior Lighting - Standard | 20 | accounting | p17 · 2020 |
| Meaford | Electrical - Interior Lighting - High Wattage | 20 | accounting | p17 · 2020 |
| Meaford | Electrical - Emergency Lighting | 20 | accounting | p17 · 2020 |
| The Blue Mountains | Interior Lighting | 20 | accounting | p11 · 2019 |
| The Blue Mountains | Ice Surface Lighting | 20 | accounting | p11 · 2019 |
| Welland | HVAC/Electrical/Mechanical | 20 | accounting | p8 · 2021 |
| Vulcan County | HVAC (electrical, mechanical) | 20–30 | accounting | p5 · 2024 |
| Duncan, North Cowichan · same table | Building Other (Electrical, Mechanical, etc.) | 25 | accounting | p17, p9 · 2011 |
| Lantzville | Electrical, Mechanical, Plumbing | 25 | accounting | p11 · 2019 |
| Tofino | Systems - mechanical, electrical, HVAC | 25 | accounting | p12 · 2009 |
| Brantford | Buildings - Electrical | 25 | planning | p10 · 2025 |
| Brantford | Site Works - Lighting | 25 | planning | p10 · 2025 |
| Greater Napanee | E25 Plant Mechanical & Electrical | 25 | accounting | p16 · 2012 |
| Kirkland Lake | Buildings and Improvements - Mechanical/Electrical | 25 | accounting | p10 · 2020 |
| Rainy River | Building Improvements - Electrical/Plumbing | 25 | accounting | p11 · 2010 |
| Rainy River | Building Improvements - Electrical/Plumbing | 25 | planning | p17 · 2026 |
| The Blue Mountains | Electrical System | 25 | accounting | p11 · 2019 |
| Bancroft, Centre Hastings, Hastings Highlands, Wollaston · same table | Electrical/Plumbing | 25–30 | accounting | p5, p4, p6, p5 |
| Brockton | Mechanical/Electrical (Heating/Cooling System, Refridgerating System) | 40 | accounting | p2 · 2009 |
| Greater Madawaska, Quinte West · same table | Electrical | 40 | accounting | p17, p38 · 2025 |
| Simcoe | Electrical | 40 | accounting | p19 · 2025 |
| Trent Lakes | Electrical | 40 | accounting | p10 · 2009 |
| Meaford | Electrical - System | 50 | accounting | p17 · 2020 |
Of 54 rows, 2 were compared with an image of their page; 52 were matched to their page automatically (the label and number appear in the page text). Follow the page link before relying on an automatically matched row. About the policies · All approved rows as JSON
Preventive maintenance
16 tasks in 2 work orders. Intervals that fall due together are one visit: the annual visit also covers the semi-annual tasks.
- 1
- 2
- 3
- 4
- 5
- 6Semi
- 7
- 8
- 9
- 10
- 11
- 12Annual
Months from the schedule start. Download the tasks as CSV for a CMMS, or ask the MCP tool get_pm_schedule for dated visits.
Semi-annual · 1 task
Source: TM 5-692-1 Maintenance of Mechanical and Electrical Equipment at Command, Control, Communications, Computer, Intelligence, Surveillance, and Reconnaissance (C4ISR) Facilities: Recommended Maintenance Practices, Table 21-3 Secondary system transformers
| Task | Page |
|---|---|
| Inspect solid insulation for discoloration | p176 |
Annual · 15 tasks
Source: TM 5-692-1 Maintenance of Mechanical and Electrical Equipment at Command, Control, Communications, Computer, Intelligence, Surveillance, and Reconnaissance (C4ISR) Facilities: Recommended Maintenance Practices, Table 21-1 Typical secondary distribution maintenance
| Task | Page |
|---|---|
| Check warning signs are in place | p173 |
| Inspect enclosure for damage, openings and corrosion | p173 |
| Clear blocked air passages | p173 |
| Investigate unusual odors | p173 |
| Inspect electrical connections for degradation and tightness | p173 |
| Inspect insulation for discoloration | p173 |
| Inspect equipment grounding conductors and connections | p173 |
| Check indicating lights | p173 |
| Clean equipment | p173 |
| Tighten electrical connections | p173 |
| Verify equipment grounding | p173 |
| Infrared scan | p173 |
| Inspect forced cooling equipment | p176 |
| Test cooling fans by simulating high temperature | p176 |
| Verify transformer alarms | p176 |
Frequencies are ISO 8601 durations in the data (P3M = every 3 months).
Open questions
- Every source here is a published planning, design or accounting life. None is observed replacement data.
- Some maintenance intervals come from TM 5-692-1, an Army manual for mission-critical (C4ISR) facilities; they may be tighter than typical commercial practice.
Know the answer? Send it with a source to [email protected].
Cite this
Citation
unfinished.one (2026). Transformer, dry-type, v0.4.0. https://unfinished.one/c/transformer-dry/v/0.4.0BibTeX
@misc{unfinished_transformer_dry_0_4_0,
title = {Transformer, dry-type},
author = {{unfinished.one}},
year = {2026},
version = {0.4.0},
url = {https://unfinished.one/c/transformer-dry/v/0.4.0},
note = {CC BY 4.0}
}Licence CC BY 4.0 · How to cite · JSON · Versions: 0.4.0, 0.3.0, 0.2.0, 0.1.0