Ontario · Single-tier municipality · population 103,988 (2021)

Chatham-Kent

Municipal website

Documents

Stated lives

52 rows, each as written in the document and linked to its page. Policies give accounting lives (amortization periods); plans give planning lives. Neither is a measured replacement age.

Detailed Asset Management Plan: Bridges & Culverts 2025

As writtenYearsSystemChecked againstPage
Bridges & Culverts Greater than 3 m70Roadwayspage textp9
Access Bridges Less than 3 m70Roadwayspage textp9
Culverts 2 - 3 m70Storm sewerpage textp9
Access Culverts60Storm sewerpage textp9
Minor Culverts60Storm sewerpage textp9

Facilities Services Detailed Asset Management Plan 2024

As writtenYearsSystemChecked againstPage
Maintenance garage (slab on grade, concrete block wall structure)100Superstructurepage textp34

Detailed Asset Management Plan: Roads 2025

As writtenYearsSystemChecked againstPage
Paved Roads (Arterial) - includes both Rural & Urban45Roadwayspage textp10
Paved Roads (Collectors) - includes both Rural & Urban60Roadwayspage textp10
Paved Roads (Local)80Roadwayspage textp10
Surface Treated Roads80Roadwayspage textp10
Sidewalks40Sidewalks and walkwayspage textp10
Facilities - PW yards, salt sheds, workshops50—page textp10
Traffic Signals - Signalized intersections25Traffic signals and other site electricalpage textp10
Traffic Signals - Pedestrian Crossovers25Traffic signals and other site electricalpage textp10
Streetlights - Light Poles50Site lightingpage textp10
Streetlights - Streetlight Heads25Site lightingpage textp10
Road Signs - Regulatory10Roadwayspage textp10
Road Signs - Guide Signs20Roadwayspage textp10
Road Signs - Info Signs20Roadwayspage textp10
Guide Rails40Roadwayspage textp10
Curbs & Gutter45Roadwayspage textp10
Surface asphalt - arterial roads (prose)15Roadwayspage textp24
Surface asphalt - local roads (prose)25Roadwayspage textp24

Detailed Asset Management Plan: Stormwater 2025

As writtenYearsSystemChecked againstPage
Linear pipes75Storm sewerpage textp11
Urban tile drains50Storm sewerpage textp11
Pumping Stations60Storm sewerpage textp11
Catch Basins75Storm sewerpage textp11
Catch Basin Leads75Storm sewerpage textp11
Lateral Services75Storm sewerpage textp11
Maintenance Holes80Storm sewerpage textp11
Oil & Grit Separators80Storm sewerpage textp11

Detailed Asset Management Plan: Wastewater 2025

As writtenYearsSystemChecked againstPage
Wastewater Treatment Plants (7)50–60Sanitary sewerpage textp12
Sewage Lagoons (2)50Sanitary sewerpage textp12
Pump Stations (55)50Sanitary sewerpage textp12
Sanitary Force Mains (70 km)75Sanitary sewerpage textp12
Gravity Mains (550 km)75Sanitary sewerpage textp12
Combined Sewers (50 km)75Sanitary sewerpage textp12
Sanitary Manholes (6600)75Sanitary sewerpage textp12
Administration Building50–60—page textp12

Detailed Asset Management Plan: Water Services

As writtenYearsSystemChecked againstPage
Water Treatment Plant60Water supplypage textp13
Wells15Water supplypage textp13
Booster Pump Stations40Water supplypage textp13
Water Towers, Standpipes, & Surge Towers60Water supplypage textp13
Bulk Water Stations35Water supplypage textp13
Re-chlorination Stations50Water supplypage textp13
Reservoirs60Water supplypage textp13
Watermains (below 200 mm)80Water supplypage textp13
Watermains (200 - 550mm)80Water supplypage textp13
Watermains (550-750 mm)80Water supplypage textp13
Watermains (Above 750 mm)80Water supplypage textp13
Hydrants75Water supplypage textp13
Administrative building50—page textp13